1) Do I need a Party Wall Notice for an extension in Lambeth?
Often yes—especially if you’re excavating near a neighbour or building on/near the boundary. Send your drawings and we’ll confirm quickly.
2) How much notice do I need to give?
Many works require 1–2 months’ notice, depending on the type of work.
3) What happens if my neighbour doesn’t respond?
A non-response is treated as a dissent, triggering the surveyor procedure so the matter can progress correctly.
4) Can one surveyor act for both parties (Agreed Surveyor)?
Yes—if both parties agree, one surveyor can act for both, often efficient for straightforward projects.
5) What is a Schedule of Condition?
A dated photographic and written record of the adjoining property before works begin. It helps prevent disputes later.
6) Who pays the party wall surveyor fees?
In most cases, the building owner carrying out the works pays reasonable costs.
7) Does a Party Wall Award replace planning permission?
No. Planning/building control are separate. The Award deals with protections, access, and responsibilities under the Party Wall Act.
8) Do loft conversions in Lambeth usually need Party Wall Notices?
Often yes—especially where steels go into party walls or the party wall is altered. We’ll confirm quickly from your plans.